Cost Application Manager
Note: This topic does not apply for the ANS module. To set up cost calculations with ANS, see the Assign Cost Libraries topic.
This Cost Application Manager, accessed from an object's Cost tab, allows the user to do the following:
-
Choose which cost libraries will be applied to each pipe and junction
-
Note that if multiple libraries are applied, costs from ALL of the selected libraries will be included.
-
-
Choose when each pipe’s or junction’s life will start and/or end
-
Specify fractional cost multipliers to be applied (for cases such as compressor energy when the compressor operates only part of the time)
The Cost Application Manager can also be accessed from the Tools menu - in which case it will show data for all Workspace objects.
Figure 1: Cost Application Manager
How Duplicate Costs are Handled
To maximize flexibility for the user, multiple cost libraries can be connected to the same engineering library. What happens if there is cost data for the same engineering item in each library? For example, assume an engineering library, compressor.dat, exists with a specific compressor "Model 100A".
Two cost libraries exist based on compressor.dat:
-
maxcost.cst ("Model 100A" installation cost = $1000)
-
bestcost.cst ("Model 100A" installation cost = $750)
If both of these libraries are connected, and All Connected Libraries are applied to the compressor, AFT Arrow will interpret the cost for "Model 100A" as the sum of the two: $1750.
There will be occasions you want cost items to be summed, and other cases where you do not. Obviously, if you have two libraries, one that tracks the maximum cost and the other that tracks the "best" cost of an item, you want to use only one cost at a time and not have the costs summed. This can be accomplished with the Cost Application Manager, by selecting only the desired library to apply.
However, perhaps the two acquisition costs do not represent the same item, but rather represent partial costs of that item that you want to maintain separately. When managed in this way, you want the costs to be summed.